Construction timeline
Timeline & Milestones

Progress, Measured.

We build with momentum. Clear timelines. Transparent payment structures tied strictly to structural milestones. Know exactly where your project stands, and where your capital is deployed.

Indicative Timeframes

The Passage of Time.

Every site is unique, but establishing realistic expectations upfront is the hallmark of a professional builder. Here are indicative durations for typical architectural and commercial builds.

Pre-Construction

Design & Documentation

8-12 WEEKS

Concept design, working drawings, engineering.

Town Planning (if req.)

6-12 MONTHS

Council approvals, advertising, neighborhood consultation.

Building Permits & Contracts

4-8 WEEKS

Building surveyor approval, final pricing, contract signing.

Construction Execution

Luxury Single Storey

7-9 MONTHS

Architectural Double Storey

10-14 MONTHS

Commercial Office Fitout

2-4 MONTHS

Industrial Warehouse Build

6-10 MONTHS
Capital Deployment

Payment Milestones.

Payments are tied to defined construction stages and set out in your contract. The split below is indicative — your contract governs the exact stages and amounts. You only pay for progress that has been completed on-site.

Architectural details
1

Deposit

5%
At Contract Signing

Secures your build slot and covers initial administrative, engineering, and permit application costs.

2

Base / Slab

15%
Weeks 1-4

Site preparation, underground services, and pouring of the concrete slab or base structure.

3

Frame

20%
Weeks 5-8

Erection of wall frames, structural steel, and roof trusses. The skeleton of the building is complete.

4

Lock-Up

20%
Weeks 9-14

Roofing, external masonry/cladding, windows, and external doors are installed. The building is watertight.

5

Fixing

30%
Weeks 15-22

Internal cladding (plasterboard), architraves, skirting, internal doors, and cabinetry installation.

6

Completion

10%
Weeks 23-28

Painting, flooring, electrical and plumbing fit-offs, final detailing, and handover.

What drives the
Schedule?

Transparency means discussing the variables. While we fiercely defend the program, certain external factors can influence completion dates. We manage these proactively to minimize impact.

Council & Authority Approvals

Town planning, building permits, and utility company approvals can vary significantly by municipality.

Weather Conditions

Extreme rain, heat, or high winds can halt external works and concrete pours for safety and quality reasons.

Client Variations

Changes made after contract signing may require re-engineering, new permits, or extended material lead times.

Supply Chain & Materials

Bespoke architectural finishes, imported stone, and custom glazing require extended procurement forecasting.

Defending the Program.

A schedule is only as good as its management. Here is how RAVCON ensures momentum is maintained from site cut to handover.

Proactive Procurement

We order long-lead items (steel, windows, custom joinery) weeks or months in advance to ensure they arrive exactly when the site is ready for them.

Elite Trade Network

We utilize a loyal, vetted network of trades who prioritize RAVCON sites. We don't wait for availability; our trades mobilize when scheduled.

Relentless Communication

Fortnightly site meetings and weekly status reports mean you are never guessing. A dedicated project manager provides a single point of truth.